Bernards Township
Settlement Talks Held On Ridge Oak Project
On June 7, the Bernards Township Zoning Board of Adjustment voted
unanimously to appeal a ruling by the state Superior Court, which had overturned the
Board's denial of Ridge Oak's proposed assisted living facility project.
The next day, June 8, members of the Township Committee met with Ridge
Oak, Inc., representatives, apparently in an effort to reach a settlement of the separate,
federal suit against the township. This suit, which is also against the Board of
Adjustment, alleges discrimination against the handicapped, and claimed the township's
zoning did not allow assisted living facilities.
However, in July 1999, the Township Committee adopted an ordinance to
allow assisted living facilities in an R-6 3-acre zone. The Planning Board then approved
plans for Sunrise Development to build an assisted living facility on King George Road
(outside of the Great Swamp Watershed).
Residents of the neighborhood in which Ridge Oak proposes to construct
their assisted living facility object to the size of the project. They said the facility
would be wider than a football field and 27 times as large as the average house in the
neighborhood. Ann Parsekian
Somerset Hills Acreage Eyed In New Open-Space Plan
On Thursday, June 8, the Somerset County Park Commission introduced an
updated master plan, which includes more than 1,500 acres of land in the Somerset Hills
proposed for open space and recreation. Included in the 1,500 acres are 279 acres adjacent
to the Lord Stirling Park in Bernards Township. The master plan suggests that Lord
Stirling Park be expanded "to ensure the integrity of the Passaic River watershed of
the Great Swamp National Wildlife Refuge and to increase the opportunities for public
recreation experiences in this area of Somerset County." Ann Parsekian
Bernardsville
Borough Council Introduces New Monster House Ordinance
A new floor-area ratio (FAR) ordinance was introduced by the
Bernardsville Borough Council. The new ordinance uses a sliding scale within six lot-size
ranges to determine the allowable floor area ratio for residential properties. Mayor Hugh
Fenwick said the new ordinance is "slightly more generous" than the current
"monster house" ordinance, which allows a maximum FAR of 5 percent (6,534 sq.
ft.) in the 3-acre zone (130, 680 sq. ft.).
In December 1999, the Community Builders Association filed a lawsuit in
connection with the existing law, contending it is too restrictive.
Under the new ordinance, lots of 50,000 to 150,000 sq. ft. have a base FAR
of 6,000 sq. ft. plus 4 percent of lot area above 50,000 sq. ft., which would permit a FAR
of about 9,227 sq. ft. for a 3-acre lot. The top lot size range of 150,000 sq. ft. and
larger would allow for a 10,000 sq. ft. base FAR, plus 3 percent for the portion of the
lot in excess of 150,000 sq. ft.
The new law also limits impervious surface to 1.5 times the permitted FAR,
plus a driveway allowance of 14 times the existing or proposed front setback.
-- Ann Parsekian
Chatham Township
Board of Adjustment Denies Deer Park Expansion Request
On June 15th, the Board of Adjustment of Chatham Township denied the
use variances requested by Deer Park, L.L.C., to expand its offices and parking lot at 700
Shunpike Road. The Board found that the intensification of use in a residential zone was
not warranted, despite Deer Park's promise to grant a conservation easement and adhere to
the township's strict environmental codes when expanding the parking lot.
The medical technology business is located in a residential zone and has
been permitted to operate there thanks to a conditional use variance given to former
tenant Transworld Radio, a non-profit institution. The Board of Adjustment had ruled in
1990 that the office space on the property should consist of only the current office
building, and not the two former residences on the property.
In addition, the Board had limited the number of employees that use the
parking lot to 65. In its most recent application, Deer Park asked to renovate the
residences as office space, and to double the number of employees and parking spaces. --
Kathy Abbott
Townhouse Proposal Scaled Down To Meet Continuing Local Concerns
In July, Sterling Properties submitted a new application before the
Chatham Township Planning Board to develop the thirty-acre property at the intersection of
Shunpike and Green Village roads. This time, Sterling proposes building 56 luxury
townhouses on this land formerly known as the Tublitz estate, a vast reduction from the
townhouse 122 units it first proposed over three years ago.
The new proposed townhouse complex, to be called Rose Valle, also adheres
more closely to the Township's building codes and environmental ordinances than Sterling's
previous plans. Rose Valle would require no height variances, would impact fewer steep
slopes, and would destroy fewer trees.
Over the past few years, neighbors, GSWA and the vigilant Township
Committee played a major role in scaling down the urbanization of this 30-acre wooded
tract.
In 1997, Sterling received approval from the Board of Adjustment for the
122-unit complex, but the project was stopped after township residents appealed the
Board's decision to the Township Committee. The citizens asserted that Sterling hadn't
justified the inordinate number of D-class variances needed. D-class variances concern a
building's "bulk" measurements, such as height and setbacks. The Township
Committee upheld the appeal and thereby denied Sterling's application for D-variances.
Sterling then appealed the denial in Superior Court in Morristown. The judge remanded the
application back to the Board of Adjustment.
In October 1998, Sterling presented to the Planning Board a 96-unit
design, with fewer, but larger units than the original 122-unit proposal. The Board of
Adjustment and Sterling proceeded to discuss problems with the number of height variances
required, construction on steep slopes, storm-water runoff, road widths, and traffic
congestion. Then unexpectedly, on May 29, 1999, Sterling attorney Barry Osmun asked the
Board of Adjustment for preliminary and final site approval before the controversies had
been resolved. The Board of Adjustment was forced to vote to deny Sterling's application
for the 96-unit complex. Kathy Abbott
Harding Township
Twp. Committee Reviews Conditional Use Ordinance
In June, the Township Committee held a public hearing at which it
reviewed the Planning Board's recommendation to amend the Township's Conditional Use
Ordinance. This recommendation addressed which Township roads were appropriate for
conditional uses such as schools, nursing homes or churches; it was made as the first part
of a complete review of the Ordinance undertaken by the Board.
The Township Committee approved the Planning Board's recommendation that
conditional uses were appropriate only on collector county roads and state highways.
Environmental Group Monitors Truck-Stop Runoff
The Harding Township Environmental Commission (HTEC) is closely
monitoring an Interstate 287 truck stop these days, studying an innovative underground
system to remove oil and grit from stormwater runoff.
The system, called an oil/grit separator, was acquired with a $20,000
grant to the HTEC from the U.S. Environmental Protection Agency, and installed by the NJ
Department of Environmental Protection and the Department of Transportation.
In use since September 1998, the system receives stormwater from the paved
area of the truck stop, swirls it in a chamber to separate out the grit, then passes the
water through a separator that allows the oil to float to the top while clearer water is
discharged below. The clearer water is then purified by a sand filter.
The HTEC grant also provided for the acquisition of automated sampling
equipment and for laboratory analysis of samples taken during heavy rains.
The HTEC has monitored three significant storms since May 1999, with
dramatic results. Samples of stormwater taken as it flows off the parking lot contain many
suspended and settleable solids. After treatment in the oil/grit separator, levels of both
sediment and petroleum hydrocarbons were reduced significantly although visually,
the water still appeared grayish rather than clear. After discharge from the sand filter,
the water appeared to be virtually clear.
The larger significance of this project is that the two NJ agencies
involved are eyeing the system for potential use at rest stops throughout the NJ
interstate highway system.
To that end, the DEP invited the HTEC to present the results of this
project at a statewide meeting in June. The project won acclaim as an excellent example of
how cooperative grants with environmental commissions can produce important results. In
this case, a number of attendees expressed appreciation that they now had concrete data to
help convince municipalities to require the use of sand filters for developments that
include paved areas. Roger Greenway
Long Hill Township
GSWA Works with Builder To Ensure Smart Development
The Long Hill Township Planning Board approved a plan to develop eight
houses on what is perhaps the finest remaining parcel in Long Hill. The new homes, to be
known as High Point Estates, will be built on heavily wooded three-acre lots along the
mountain ridge of Long Hill Road, affording spectacular views that stretch some 20 to 30
miles to the north and south.
That's the bad news. The good news is that the project is a model of
developing with a lighter touch. The applicant, Michael Menza, worked closely with GSWA,
re-drawing the plans to meet virtually all of the goals of the Ten Towns model ordinance
for stormwater. Steep slopes are being protected under Long Hill's strict ordinance;
utilities will be placed under narrow, shared driveways; and with the exception of a
75-foot perimeter around each of the proposed houses, most of the remaining parcel will be
protected by a conservation easement. A good community effort!
Another applicant proposed a single-home subdivision on Meyersville Road
and was turned down by the Planning Board. The public raised issues of inadequate
stormwater management, an oversized house for the neighborhood, and the fact that this
would be a flag lot. Len Hamilton
Madison
5-house Subdivision Allowed On Land at 300 Madison Ave.
The Madison Zoning Board of Adjustment voted in May to allow a
five-house subdivision with 15 related variances on the three undeveloped acres at 300
Madison Avenue. Despite compelling testimony related to both planning and environmental
issues and unanimous opposition by neighbors in attendance, the Madison Environmental
Commission, and the Harding Township Engineer, the Board voted to approve the application.
Members of the Board apparently agreed with the applicant's view that
development on the land, which a 1984 Zoning Board of Adjustment ruled should be kept as
open space, is inevitable.
Neighbors concerned about the loss of the three-acre woodlands were not
without some victory. They mitigated stormwater runoff problems by hiring engineer and
planner John Thonet to present testimony at prior meetings. As a result of his
environmental expertise, the Board imposed several conditions related to improving
groundwater re-charge systems and increasing a conservation easement to include an
existing natural depression which currently acts as an aquifer re-charge zone. Judy
Kroll
Residents Form Madison Matters After Developer Razes Home,
Trees
On Monday, May 15, just three weeks after the Planning Board denied an
application for a non-conforming sub-division at 144 Loantaka Way, developer Joseph
DeMarzo demolished the century-old manor house on the property to prepare to construct one
new home. Adding insult to injury to the hundreds of Madison residents who opposed the
sub-division for both historical and environmental reasons, DeMarzo then removed numerous
large trees from the property. Witnesses were dismayed that several trees were removed for
no apparent reason, forever transforming the lot from wooded to nearly clear-cut.
On a positive note, the builder's seemingly vengeful destruction has
galvanized citizens to form a committee called "Madison Matters." They seek to
preserve the historical homes, mature trees and original lot sizes that make Madison
residences so desirable, and, incidentally, more beneficial to the Great Swamp. -- Judy
Kroll
Morris Township
Kimmerle Associates Seeks Variance to Build Duplexes
Kimmerle Associates has presented a plan to the Morris Township Board
of Adjustment to build four duplexes (eight homes) on a one-acre site adjacent to the
Spring Brook Condominiums on Mount Kemble Road. The site, which falls within the Great
Swamp watershed, is occupied by a single-family home that Kimmerle claims is
deteriorating. In seeking a variance to the zoning, Kimmerle has asked for the Board's
approval by reasoning that dense housing on small acreage is happening all over.
Residents of the condominium association and certain Board members are
concerned about setting a precedent, whereby landowners on Mt. Kemble might seek variances
in the future to develop dense, condominium-like complexes on land zoned for one/two
family homes. Space for parking and stormwater runoff are also concerns at the site. --
Terry Hudzina
Jockey Hollow Top Six Draws Concerns of Engineer, Geologist
Harvey Caplan's Jockey Hollow Top Six development bid before the
Morris Township Planning Board is about to come to a close. Soil destabilization pictures
taken by Harding Township engineer Robert Fox unearthed evidence that soil erosion
continues on the already developed Top Five section. Concerns of soil erosion on the yet
undeveloped Top Six portion of the project are rooted in the fact that the slopes there
are steeper than those of Top Five, and therefore less likely to be controllable.
Mr. Fox's review of the engineering study presented by Mr. Caplan's
engineer, Robert Kirkpatrick, portrayed the plan as full of holes. Perhaps never before
has there been such conflicting testimony between opposing engineers. Areas of conflict
included the impact of development on stormwater and soil erosion; downstream effects; the
efficacy of current engineering technologies for building on steep slopes; and the volume
of stormwater that would leave the site after development and its potential for causing
problems.
An earth-shattering historical review of the Ramapo Fault by geologist
Ralph Costa of CH2M Hill, a Philadelphia firm with offices in Parsippany, also helped to
shake up the possible approval of Caplan's present proposal.
According to Mr. Costa, the land that Top Six would be developed on falls
near the Ramapo Fault line. As a result of previous tremors along the fault, the bedrock
is fragmented. If disturbed, for example by blasting, the bedrock may exhibit stress
failure, leading to seeps, landslides and subsequent soil erosion that are not presently
evident. -- Terry Hudzina
One person Can Make a Difference: A Citizen Shapes a Board
Decision
An example of how one person can make a difference occurred at a
meeting in which representatives of the AT&T building off of James Street came before
the Planning Board seeking variances for work to be performed on their parking lot,
entrance and delivery area.
A citizen at the meeting raised concern about approximately 600 parked
cars and the petrochemical pollution that might occur from run-off into a storm drain
system that emptied into Great Brook - a feeder stream of Great Swamp. The Planning Board
seeing some merit in the questioning, asked the Township engineer to work with the
representatives to find a financially feasible solution to retrofitting the storm drains.
The result: Oil separators will be used to help prevent contamination of
Great Brook from petrochemical run-off. The message: Get involved, become a swamp watcher
in your town AND remember: Just as one picture tells a thousand words, so too can one
person make a world of difference! -- Terry Hudzina